Moving Ahead - October 2006

October 27 2006

  • SOUTH MEDFORD INTERCHANGE – Completion of I-5 Detour Bridge Marks First Construction Milestone

    The first steel reinforced concrete beams, 110 feet long and weighing 15 tons apiece, are sitting on the first of nine bridges under construction as part of the South Medford Interchange project. Two large cranes immediately lifted the beams in place on what will be a new bridge over Larson Creek, connecting Barnett Road with the new interchange. “That’s just a snapshot of the work that has been going on in the construction zone,” said ODOT Public Service Representative Bill ...
    Read More